For the leading force in the transformation of the electricity market we reviewed the Environmental Monitoring Plan for the building of a new 380 kV power line between Bisaccia and Deliceto. Following Ministry approval, we continued with the environmental measurements provided for in the plan: vegetation, bird life, landscape, noise and electromagnetic fields. We also drew up an excavation earth sampling plan and a landscape report.

Tipologia: 
Environmental Monitoring Plan (EMP)
Committente: 
Terna S.p.A.
Area: 
Campania – Puglia